PO Creation From SO, Third Party

0 Kudos

Hi All,

We have a process where a PO is directly created from SO from the schedule line (third party config).

Now for one material (Lets say material A) the PO is perfectly triggered, But for another (material B), PO is not triggered.

In SO, Item cat and Schedule line cat is same for both the orders.

Both material is having same material type, MRP 2 -->procurement is F (external).

Where else should I check?

Regards,

Supratik

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Hi All,

Thanks a lot for replying.

we have found the solution for this issue. The PR was automatically triggered for sch. line, but the PO was not getting triggered due to GTS block.

Clearing the GTS block will enable PO auto trigger.

This is logged under sales order status overview.

Thanks a ton for helping.

Regards,

Supratik

former_member220617
Contributor
0 Kudos

Dear Supratik,

Check the below settings .

1. check general item category group is BANS or not ?

2. check both material purchasing group is created or not ?

Regards,

C.B Reddy.

sridhar_v
Active Contributor
0 Kudos

Hi Reddy,

Schedule line is determined based on

Item category + MRP type.

there fore did you compare the both the materials MRP data?

I strongly feel when one material is creating PO which is maintained in Schedule line why cant the other.

I suggest check both the MRP data.

There are occasions when some clients do maintain ME01 and ME11 as well, check them if it is relevant to you.

Thanks,
Sridhar.

prashant_sharma21
Contributor
0 Kudos

Hello Supratik,

Check the below points,

1. check whether delivery block is there for material B?

2. Check whether Purchase Info record is exist for material B or not?

3. check any deletion indicator is set for material B??

Thanks

jobis
Contributor
0 Kudos

Hi Supratik,

Also check if the item's delivery is confirmed in sales order schedule line..

Thanks

Jobi