Hi,
while trying to create planned order in APO I always receive the error message for the end product:
"
Message no. /SAPAPO/RRP251
While creating an order, the system encountered problems, such as, for example, no available components or components that are available late, orders that could not be scheduled, and so on.
The system attempted to solve the availability problems by using alternative procurement options. This was not successful. The order could not be created.
Check the exceptional situations in the planning protocol, under Display Logs, and deal with the causes of the exceptional situations if this is possible or necessary"
I have no clue why.
I checked the product master, semse to be ok. The procurement type is E - correct.
I checked the master recipe as we run APO with PP-PI:
I see there is 0 for setup time and no activity type assigned.
-machine time: 1 h
- labor time 4 hours but no activity type assigned
might this cause the issue?
control key is active for scheduling and capacity requirements.
Production version is ok.
PDS seems to be ok, the activities are assigned to PI phase only
what can be the reason?
I am not able to create a planned order for this product.
thank you for all helpful input!
kr,
Pilvi
Hi Pilvi,
Message /SAPAPO/RRP251 is a bit generic and can be raised in different scenarios under different conditions.
At the Product View, in menu Goto -> Display Logs, are there any other logs shown, both in Planning Logs and in Scheduling Logs tabs?
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tiago,
that was the only eror message. the other once were just warning:
"
Message no. /SAPAPO/RRP630
You want to carry out planning for a product for which orders with characteristics exist. When analyzing the characteristics, the system detected that for one or more of the orders, certain characteristics have not been assigned values or have been assigned incomplete values. In other words, the characteristic has an initial value or an interval or multiple value assignment. However, there are also orders where these same characteristics have been assigned values. This combination of characteristics leads to assignment problems in planning which cannot be solved by the system (See also SAP Note 526883).
The system executes planning without taking any special measures in regard to this combination. Because of this particular combination of characteristics, shortages and surpluses may occur.
Check the result of planning. Check the orders for characteristics without values and if necessary change the value assignments.
If characteristics that have not been defined occur often, and do not affect planning, you can exclude this message from the planning log in Customizing of Exception Groups for PP/DS.
"
br,
Pilvi
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.