PS ( project systems) Budget control issue with MIGO

0 Kudos

Hi Experts,

I need your help to sort out the issue let me explain:


Availability Budget of WBS element number XXXX is 200 $.

PO raised for the same WBS for 200 $.

User has decreased the budget from 200 to 150. Now PO amount 50 $ has been exceeded the actual budget.

Requirement is while doing MIGO it should not allow to post the exceeded amount for PO and expecting to throw an error saying that budget 50 $ has been exceeded for WBS element XXX.

Is there any sap OSS note or any solutions to meet this requirement ?

Accepted Solutions (0)

Answers (1)

Answers (1)

sammar81
Employee
Employee
0 Kudos

Hi Lokesh,

In SPRO settings for the  Budget Tolerance Limits select the target group as ++. It should work..

Regards

Sammar

Former Member
0 Kudos

Hi Lokesh,

How do you decrease the budget? Supplement? Transfer?

Do you execute the transaction CJEN and CJBN?

Please also consider that the AVAC is not active during MIGO process (see SAP note 46209).

Best regards, Gordon

0 Kudos

Hi Sammar,

Thanks for your response.

We already maintained the tolerance limit.

Regards,

Lokesh E

0 Kudos

Hi Gordon,

To test on this scenario, I have increased the PO amount from 200 to 250 SGD.

To do this change I have used CJBW to deactivate budget control and make changes on PO amount.

Again reactivate the budget control in CJBV.

Now I am trying to test the MIGO where the PO amount is more than budget amount.

During this time I am expecting to get some error, but it does not happening and MIGO is posting without any budget exceed error message.

Please give your suggestion.

Regards,

Lokesh

Former Member
0 Kudos

Hi Lokesh,

In order to get AVAC check during MIGO, please apply the proposal given in SAP note 46209.

Best regards, Gordon

Former Member
0 Kudos

Please check notes: 142866 and 755495.

0 Kudos

Thank you Shishir,

I will check the provided notes and get back to you.

Regards,

Lokesh E

Former Member
0 Kudos

Hi Lokesh,

Check SAP note 464209.. You can also check instructions in note 696362.

Following note is also useful

324486 - Availability control for goods receipt MIGO

Regards

Tushar

Former Member
0 Kudos

Hi Lokesh,

I am also facing same problem.

Budget is 3mil and actual posting allow 6mil. Budget control check is not functioning.

And it showing negative budget, so please suggest on this issue..

Regards,

Radha krishna.