Hi gurus,
i have given budget for project.
wbs element | budget |
AS-00000036 | 50000 |
AS-00000036-01 | 10000 |
AS-00000036-02 | 10000 |
AS-00000036-03 | 10000 |
AS-00000036-04 | 10000 |
AS-00000036-05 | 10000 |
AS-00000036-06 |
Then i am trying to post cost against wbs element is AS-00000036-06 it's not allowing, it says budget exceed.
but i want book the cost against AS-00000036-06 without budget.
how to deactivate budget for particular wbs element.
please suggest.....
thanks for your reply Shishir
You can change status of projects as well as single /range of WBS element in OPSX
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sushrut,
Thanks for reply, as per your answer OPSX transaction we will reset status, but i want book the cost without budget for this wbs AS-00000036-06. i want to deactivate budget for particular wbs element.
Hi Shishir,
my client requirement is for this wbs element AS-00000036-06 they wont consider budget, but what ever the actual cost booking for this wbs they want to consider only actual cost.
please suggest....
As I told, it's not possible as AVAC is still active for project, so you are getting error. Further your actual will not get generated. Also it affect the whole structure.
Possible Solutions:
1) You can deactivate avac for your whole project using CJBW (But for a single WBS not possible): In this case your if your budget is 0 then will not check.
2) Go with my first reply: enter budget on top level only, as you have already budget on top WBS.
please send me the screen shot of the status of the WBS elements transaction code CJ20N also note that when you do budgeting it is required that person responsible be always maintained in the WBS element
this error is due to status AVAC is still active for the WBS element
Remove the status with above procedure.
Remove the budget and Release
Dear Siddu,
i found out solution and it must work
please follow following steps
>first deactivate availability control by CJBW
>then go to CJ20N Set status of the WBS element to DLFL(at top of screen ,Edit-->status-->deletion flag -->set)
>then again go to CJBN and reactivate the availability control
>once reactivated,go to CJ20N and check the status in status bar there is no AVAC set for the WBS element
>just once again reset the status and remove deletion flag and start posting over to the WBS elements
Please mark as correct when it is done and award points
hi,
follow the following steps
Deactivate the availability control CJBW(AVAC is Removed)
Then goto CJ32 and remove the budget which is released and save(document is posted)
Then go to OPSX and change the status of the WBS ,remove the status BUDG
Go to CJEN and reconstruct project info data base
CJBN activate the availability control
Next time when you post the document system shall not check the budget for that WBS element
try and let me know
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For this scenario, Technically not possible, if you want to book cost without budget on particular WBS.Apart from this, I want know that what is the business scenario behind this requirement.
Another work around, you can assign total budget only on parent WBS that is on AS-00000036. No need to assign on its children WBS. And when you try to book cost on AS-00000036-06, system will pick budget from its parent AS-00000036 as this is parent WBS.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.