on 12-11-2014 12:54 PM
Dear Expert,
We are working with project system assigning maintenance order to WBS through of t-code ADPMPS.
When we run the any report from PS (e.g. S_ALR_87013558) we find the values below in one WBS:
1) Budget/Actual/Rem.Plan/Assigned/Available (S_ALR_87013558)
Budget = 428000, Actual = 0, Commitment = 65936, RemOrdPlan = 107960, Assigned = 173896, Available = 254104
To this scenario I have just one maintenance order assigned to this WBS.
However when I go into any maintenance cost report I cannot find the cost as shown on PS report.
My planned cost on MO is $ 123000 (commitment and planned). Even any report that I run to this order I can not identify the values as shown on column total assigned on PS $ 173896 (commitment $ 65936 + RemOrdPlan $ 107960).
Does anyone have any suggestion/explanation to this difference?
See screenshot below
Wagner Silva
Hi,
In screenshot of Maintenance order, only plan cost is showing & no actual cost is there. So you are not getting any value in maintenance cost report as this report only shows actual cost (i.e. plan cost settled to WBS using KO88). Apart from this WBS budget report S_ALR_87013558 will show any amount if get consumed from this.
So you need to settle this plan cost then it will show you in maintenance cost report.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Silva,
Would suggest you to go through SAP note 178837 to understand how Assigned value calculation works.
178837 - Availability control: Incorrect assigned value?
Regards
Tushar