Add material to incompletion log for VA01

0 Kudos

Hi ,

I have a requirement where I want to add material to incompletion log. System should send a warning to add material number and if document is saved without entering material number no further documents should be created.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

anita_patil3
Explorer
0 Kudos

Hi;

You can create incompletion log for sales order item VBAP-MATNR field.

This can be done with standard incompletion log settings.

Hope would be helpful.

Regards;

Avinash

0 Kudos

Hi Avinash,

Thanks.But at item level we assign incompletion procedure to an item category.SO if I enter a material number ..I can assign incompletion for order quantity,weight ,etc ..and since material comes at item level it can not be assigned to header also.Hence this is a bit tricky situation I guess.

Shweta

anita_patil3
Explorer
0 Kudos

Hi Shweta;

I am sure that can be done in header level incompletion procedure as well. Insert VBAP-MATNR in header incompletion.

Regards;

Avinash

0 Kudos

Hi Avinash,

If we enter VBAP-MATNR in header incompletion then what should be given as a screen?

Shweta

Lakshmipathi
Active Contributor
0 Kudos

In completion log, maintain as follows at header level and try creating a new sale order.

VBKD::::POSNR::::KBES:::01:::X

G. Lakshmipathi

0 Kudos

Hi Laxmi,

Thanks.Yes it works as it send order into incompletion log but for completing the data it is taking to PO number screen which is not correct I guess from a business perspective.Looks like it will be a change in user exit.But thanks a lot

Shweta

anita_patil3
Explorer
0 Kudos

Hi Shweta;

I do not think any specific material related screen can be assigned there. But this is just a indication for data completion so I you use it as work around. I would suggest the same in spite any more development.

Hope will help you.