Hi,
We have multiple lines produce the same product at the same time. There are one production version/PDS per line for a given product. Does anyone know if there is function in PPDS that could schedule production on multiple lines at the same time? Currently, the system plan the lines one by one. For example, it will load line A first then load line B... What we need is to start producing the same product on multiple lines same time.
Thanks,
Rick
Hi,
You mean you want to schedule same order on two lines at same time so you complete production in less time?or two different orders?
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you want two have two differnt orders then one way to control is to use some lot size setting like may be maximum lot size or fixed lot size so that you always get multiple orders on same date during planning then you can try uing Heuristics SAP_MULT_SCH and if you are using repetative manufacturing then there is heuristics for loading lines equally.
Regards,
Santosh