In SAP SNP, I have a requirement to run a job on every last Saturday in every month(Currently the job is released manually every month).
I have defined the last Saturday of every month as a public Holiday. But I am not able to enter this Holiday Calendar in the factory Calendar.
Can this requirement be achieved using standard SAP or any enhancement is required? If enhancement is required, can you provide inputs on how to design it?
Thanks,
Sunny
Also check with below BADI's in SE18.
CALENDAR_DEFINITION
SCAL_CONVERT_DATE
Regards,
TP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunny,
First you have to assign the holiday calendar to the factory calendar in SCAL and then in SM37 you can assign the factory calendar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.