Hi,

I'm trying to migrate planning costs from an old System to the new SAP solution. We choosed to use Easy Cost planning for cost plans. So  I tried to do a recording but the issue is that when I'm trying to enter  the type of ressource, quantity and amount, the fields are not saved into the recording. Is there some other way to do this ( Batch Input, BAPI or FM)?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Ismael,

You can use BAPI_PROJECT_MAINTAIN

Check below link

ABAP calls to create Easy Cost Planning in Project Systems - Product Lifecycle Management - SCN Wiki

Regards

Tushar

Former Member
0 Kudos

Thanks  a lot , I will try this way and get back to you guys with the result!