Hi Masters,

I cureently active for year end closing support activity, could anyone explain about this PS budget problem symptoms?

and what tcode is to display wbs element budget consumption?

Any solustions from all of you really helpful to me,

Thanks,

Regards,

Dio

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Dio,

Use t-code CJ31, type in your WBS-element P-1407SCC-TTES0422.CZSI0 and next select from the menu Extras > Availability Control > Analysis.

Alternatively just use program BPFCTRA0 from SE38 (that is the same thing).

Regards,

Paulo

Former Member
0 Kudos

Dear Paulo,

Actually I already solved my issue, by comparing the item 3 in simulate miro where as the budget exceeded happened by execute s_alr_87013558, and then advice the user for additional released budget according needed in miro,

anyway thanks for the help,

Regards,

Dio

Paulo_Vitoriano
Active Contributor
0 Kudos

Hello Dio,

Just FYI for any complex logic of availability control (when you have exempt cost elements) standard reports like S_ALR_* will not show the correct figure for remaining budget, but only the ABAP report that I mentioned earlier will. 

BR,
Paulo