Hello All,
Kindly guide as what will be the best C-Project structure to
handle the below which might involve:
1. Resources from Multiple Company codes under same controlling area
2. Resources from Multiple Company codes under different controlling area
My scenario is a New Product Development scenario in which resources from
multiple part of the world will collaborate. It also needs accounting integration
with Backend WBS elements, time confirmation need to happen using CATs. Should multiple CProjects need to be created and
for each company code (as a sub project) and connected using Tasks assigned to Sub Projects ???? Please guide.
Thanks,
Sachin
Hi Sachin
Yes you would need multiple C projects in case of Different Controlling Area. because from PS end you cannot have two controlling areas within a single project..so for companies falling under different Controlling areas you would require to create separate projects..
for the different companies in same controlling area you can use the same cproject as in PS you can have different company codes working in one project..
hope it helps..
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Sammar for the answer and confirming. I think one option might still work for multiple controlling areas: For multiple controlling areas, creating Multiple PS Projects (one each for controlling area) , and still creating one CProject with multiple phases. Each CProject Phase Account Assigned to one PS Project WBS Element (with unique controlling area) and keeping CProject Project Definition having no account assignment. I hope this set up should also work for Multiple Controlling for a Global Project using resources from all parts of world. Do you agree??
Thanks,
Sachin
Hi Sachin,
This will not work.. As you don't have org. structure maintained in C Projects. what happens is once you account assigned it to the PS Project.. The project profile created in PS for Integration of cproject Phases and PS Project takes control. And in Project profile you can enter only one Controlling area.
therefore for multiple Controlling Areas you definitely have to create separate C projects linked to separate project profiles in PS..
For same controlling area you can go with different phases of the cproject as different company codes..
Hope its clear now..
Regards
Sammar
Sammar one last question. As you mentioned for different controlling areas it will be different C-projects so should I use CProject's --Sub Project gameplan (Cproject multiproject theory that is assigning the individual CProjects to Tasks belonging to an umbrella cproject), Basically from reporting perspective I wanted to bundle multiple CProjects. Do you advise this or a CProject Program concept (Also part of CProject MultiProject theory)
Regards,
Sachin
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.