on 11-27-2014 11:07 AM
Hi
Appreciate if someone could help.
I have no Network Type defined in the system and no Network Profile attached to Project Profile. The WBS element is released and I can post Finance journals against it.
In CAT2, I book time against the WBS element using a standard data entry profile with "No Approval Procedure " and "Assignment of personnel cost to Master cost centre"
In CAT5 when I try to post, system says "Nothing to post" . Do I need to have Network defined in the project for booking actual time and value against a WBS ?
I have no problem in posting to CO (CAT7).
As a matter of fact , from PPM I am able to book planned time and cost against the same WBS.
Thanks in advance.
Hi guys,
After doing CAT7 I am seeing the CO document in KSB5 but those are not showing up in CJI3
Is it weird ? Does it have something to do with cost elements involved ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Sammar & Paulo for the help.
Now I can see the actuals in CJI3 - The reason why I could not see earlier was due to the authorisation restrictions of the test user is which I used.
Now it is clear to me that I don't need network & activity in a project to book the actuals in CAT time sheet.
Regards
Sree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sree,
Time booked against the WBS goes the CO area only using CAT7, which in your case is working as expected.
this is standard behaviour of SAP. CAT5 is used to transfer cost when time is booked using network activities.
Hope it clears your doubt.
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank Sammar for the reply.
If I would like to see these values in CJI3 (Project actual line items ) , I need to have Network defined in the project and book the time against a network - Not WBS. Is it that way ?
Once network defined under a WBS, Is it possible to book the time against a WBS and the value to be shown in CJI3 ?
Thanks again
Sree
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.