Is it possible to extend the existing time profile of an activated planning area

Former Member
0 Kudos

Hi Experts,

We are currently working on a development system with a two year horizon in time profile, soon we will move to quality system where we need to have a ten year horizon.

Question 1 - We want to extend the time profile horizon in development system, is this possible?

Question 2 - how can we change the horizon of the time profile on quality system? The only solution I can see is, to move to quality system and while activating content in quality system we can load a ten year horizon time profile. Is this the recommended solution?

Regards,

Aditya G

Accepted Solutions (0)

Answers (1)

Answers (1)

Krishna1
Participant
0 Kudos

You should be able to do it...with 3.0.2, you can change time profile...

Key is how are you transporting code fro Dev to QA