on 11-18-2014 2:47 PM
Hi all,
I created a Change Request (ZMCR) with two follow-up Change Documents (ZMMJ) in scope.
For one Change Document, I made changes to the system and imported the TR into production. The final status of this is now "Imported into Production".
For the second Change Document, I withdrew the change document. I did not create any TRs or whatsoever. The final status is "Withdrawn".
My expectation was, that I can now bring the Change Request to a final status (preferably "Confirmed" or "Realized"), as the change (or part of it) have been implemented.
But I can only set "Scope Extension" or other early status values ("Validation" etc.).
Can anyone explain, if (and why) this is standard behaviour?
And can anyone guide me how to bring a "half-implemented" Change Request to a good end?
Thanks,
Jan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jignesh,
I have the following settings:
Except the system role, it looks similar to your screenshot.
I entered a system role (Dev. System) but no effect.
The "required status values for successor" do also look ok:
ZMMJ-E0010 is Withdrawn
ZMCR-E0005 is Realized
Any further settings necessary?
Thanks and Regards,
Jan
One follow-up:
When I create an additional ZMMJ and bring this to the final status "Imported into production", then the ZMCR can be closed as wanted.
With other change documents (ZMAD, ZMGC) this does not happen.
Problem is, I cannot create an additional ZMMJ all the time when running into the described trap.
Regards,
Jan