I am transferring unreleased phases and tasks from CProject to PS but in the PS all WBS elements have ==released== and ==master data lock== status. What settings should I check in order to keep the status in the PS same as in Cproject?
Hi Kiryl Bletsko,
in the cProject 4.0 there is unfortunetely no status mapping logic between cProject elements and the replicated WBS in the ERP PS. In other words, if the WBS elements are created, the status released (REL) and master data lock (MDLK). No standard functionality can change this system behaviour beside a Badi method, which has only the possibilty, not set the MDLK.
It is documented in the note 927960 & 1003599.
An own report to synchonize the status is from technical view no problem. If anyone has it, please post it.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.