Dear friends,
There are two scenarios.
1. PS is Integrated with TR, So the posing done in Treasury relevant to WBS comes to PS actual cost which is consuming the budget,for the same we had exempt the cost element 2020200001, and now user can post the entries. but the Report S_ALR_87013558 still considering the TR entries and showing the budget in negative.
Can we developed new report in report painter which does not consider the entries posted for CE 2020200001.
If you have other solution please guide.
2. One of the WBS in which i check the actual and commitment are correct with proper cost element still available budget does in negitive.
Please guide for the same.
I had run CJEN, CJBN AND Also the program RKANBU01(For which commitment is updated compared to earlier ) and RKACOR04.
Please suggest
Thanks
Yogendra soni
Hi Yogendra,
the standard report S_ALR_87013558 always picks up all the costs booked against the WBS. It doesn;t take into account the exempted CEs.
If you want to see the actual available budget for WBS you need to develop a Z report.
for the Point No. 2 I am not clear what the issue is? Can you elaborate on that a bit more? And if possible can you put screen shot of the error?
regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Case1. 2020200001 is exempted CE.
For the WBS Element ES-BJ.I.D.C0.IM.F cost is around 53,800,000- in CJI3 booked against the CE 2020200001,
S_ALR_87013558 REPORT I can the see the Actual cost around 53,800,000 for WBS ES-BJ.I.D.C0.IM.F.
Can you pls suggest for the same.
Case 2.
For this wbs ES-BJ.C.I.MC.W .L2.CA budgte goes is negitive -28454
Any suggestion.
Thanks
Yogendra Soni
Hi,
for case 1&2 can you check in CJ31 or CJ30 whats the assigned value and available budget?
Also you can check the Availability Analysis report for these two WBS elements in CJ30/Cj31 and it will provide you with the details on the exempted cost and cost where the budget is being checked.
To create a Z report for your accurate budget availability considering the exempted cost element you can follow the below logic to create a Z report
1. Find Budgeting happens Annual or overall (Object currency or controlling area currency)
If TBP1C-BPGE = ‘X’ overall budget
If TBP1C-BPJA = ‘X’ Annual budget.
If TBP1C-BPGE = ‘X’ and TBP1C-BPJA = ‘X’ overall budget and annual.
2. When budgeted overall
Get entries from BPGE using the following input
OBJNR (of WBS)
WRTTP = 42
BPGE-WLGES is Assigned budget
BPGE-WLGEV is distributable budget.
3. When budgeted Annual
. Get entries from BPJA using the following input
OBJNR (of WBS)
WRTTP = 42
BPJA-WLJHR is Assigned budget
BPJA-WLJHV is distributable budget
Hope it helps..
Regards
Sammar
Thanks Summer for update.
I am in process of developing the Report in Report painter as you suggest.
Also regarding that negative budget issue CJ30/CJ31 etc are correct, I has raised the Ticket to SAP and they suggested some notes to implement.
We are in process for implementing the notes.
Thanks
Yogendra Soni
Hi Yogendra,
Please check CJI3 (Actual cost) & CJI5(Committment Cost) report and compare with your S_ALR_87013558.
Regards,
Avinash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yogendra,
Please ensure that there are only green lights (no red or yellow) for assignments in transaction CJVC, as this can impact the reporting values and show values that are not true simply because elements were not assigned in CJVC.
In case you having negative assigned value in CJ30 (or error 00208 in ok field -see SAP note 1414563, case A), the correct sequence is to execute the program RKANBU01, RKACOR04. Then, transaction CJEN and CJBN.
Please do share with us the result of my recommendation.
Best regards, Gordon
Hi Yogendra,
Just try to deactivate availablilty control, refresh project data base and activate the availabilty control and proceed
1. deactivate availability control: CJBW
2. Refresh data base: CJEN
3. Activate availability control: CJBV
Regards,
Avinash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.