Hello PS Experts,
I get a WBS budget exceeded error while posting a document. Below is my Project set up.
P-00008231-> Main Project
P-00008231 -> WBS with IM position ID
P-00008231-00010 -> Lower level WBS
When I try creating a invoice with WBS P-00008231-00010 I get the following error.
In document item 001 WBS element P-00001-001, budget for WBS element P-00001 for fiscal year 2014 was exceeded by 126,658.31 USD.
When I check the WBS P-00008231 the overall budget is 3,101,036.00 USD however there is no budget assigned for FY 2014. The entire budget has been distributed to lower level WBS P-00008231-00010.
The WBS P-00008231-00010 has current budget and distributable budget of 3,101,036.00 for overall period.
So I am trying to return the budget from P-00008231-00010 (Lower level WBS ) to P-00001 (WBS with IM position ID) using CJ38. So I can assign this to
P-00008231 FY2014.
However I get the error Overall budget less than cumulative budget.
Please advice.
Hello All,
I got update from the SAP team, and there budget inconsistency in most of the project.
You can check this by executing the report BPFCTRA0 for the relevant project, then enter
=SUM in the ok-code field and hit enter -> a pop up will appear which states that inconsistet assigned values exist. Please execute the following steps to fix those inconsistencies and to avoid them in the
future:
Implement the correction of the note 1580075, and then run CJEN and CJBN for all projects.
This has resolved the issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Varshal,
I cannot delete the planned value either. I can only see the budget or planned values till FY 2013.
I get the error
Overall plan value less than cumulative plan value
-
WBS Element: 19417: 0.00 < 3,101,036.00 (USD)
Message no. BQ058
The total plan value 0.00 USD in WBS element WBS Element: 19417 is less than the cumulative plan value 3,101,036.00 USD.
The cumulative plan value is derived from the total of the annual plan values.
I did check the SAP note. I will need to create the program first and then run it. I will check how can I go about it.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
My Guess was correct. There is an entry of KBUD for FY2002 in the BPJA table.
Here are my guesses in the steps followed previously, please correct if I am wrong:
My proposed solution:
Hope it helps!
Thanks and Regards,
Varshal Kachole
Hi,
Also Please consider the recommendations in http://service.sap.com/sap/support/notes/1145955
Hope it Helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Shishir,
I tried using CJ35 yet I get the same error " Overall budget less than cumulative budget ".
@Varshal _ when I check these tables I am not sure what am I looking for. What should be the Object number in the table. I tried entering the object number for project/BS(from PROJ and PRPS table ) but this is not the correct entry.
Also let me know which tcode to you need the sreen shots for ? IM52/CJ30 ...???
Thank for all for your support.
Hello Shishir,
NO luck with that as well. I have run CJBW, CJEN and CJBN. Yet the issue is the same. I has raised an OSS last wednesday with high priority and yet there is not response from SAP.
However I would really like to thank all the experts for their suggestions. In case you have some other inputs please let me know.
Thank you.
Mandar Inamdar
Hi,
The Only other possibility that I can think of, is the FY which is not visible in CJ31 is holding the Budget.
This can be easily analyzed with the help of Budget Tables, but since you have already raised the issue with SAP, lets wait for their analysis and the possible solution.
Thanks and Regards,
Varshal Kachole
Hello Sammar,
There is budget available for the project at overall level. As mentioned in my issue, the erro says budget exceeded for FY2014.
"budget for WBS element P-00008231 for fiscal year 2014 was exceeded by 126,658.31 USD."
I some how need to move this budget to WBS P-00008231 fy 2014 from P-00008231-00010.
I have also included S_ALR_87013558 and CJ30 screen shots for reference. Please check.
Thanks for your continued support.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mandar,
You can do it in CJ30 as well. Go to CJ30 and FY2014 and remove the budget from the level where you have assigned it wrongly and assign it to the right wbs? What's the issue?
In your screen shot you are still displaying budget values at overall. You need to change it to FY2014 and then rectify the error.
Regards
Sammar
Hello Shishir/Varshal,
Thank you for your quick respone. I had already tried returning budget from FY 2014 and then from Overall. However when I return budget from FY i get the error
MANA01-C1: Safety & Loss prevention: 3,101,036.00- (USD)
Message no. BQ023
I have included my CJ38 screen shot for your reference. Appreciate your help here.
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mandar,
In your screen shot you don't have amount which you can return. As the current budget column for thre WBS is showing zero value. Are you checking the right WBS for return of the amount..
You can fix it in CJ30 also,, as said by Varshal and Shishir just check for the amounts you have distributed in All the FYs and for all the WBS and sum total shouldn't be more than the overall budget..
Hope it helps..
Regards
Sammar
Hi,
Cumulative budget is the total of all Financial Year Budget. And if you assign budget on overall and get distributed to FY year level then you have take care that your current overall budget must be always higher or equal to your cumulative budget. This is standard.
Correction steps should be followed as Varshal explained. Further your need any help, reply.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The error and the description is self explanatory.
Ideally this error appears when the Return is attempted from the Overall Only despite the fact that the Budget is also available for the Fiscal Years as well.
The Correct Step should be:
Hope it helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.