Hi,

We need to migrate the actual costs posted in the Legacy System (R/3 4.7) to ECC. The data team needs to know which table/transaction they can use to get the actual costs. I have suggested them to use table COEP but they looking for some alternative.

Can anyone suggest how shall we go about the actual cost migration.

Any help will be highly appreciated.

Thanks

Mohammed T Haque

Accepted Solutions (0)

Answers (2)

Answers (2)

sammar81
Employee
Employee
0 Kudos

Hi,

In addition to COSP and COEP you can also use RPSCO with value type  4 and 11. This table contains all the costs from the projects..

Regards

Sammar

Former Member
0 Kudos

Hi,

You should try tables COSS and COSP -

value type as 4 and 11

version as '0'

these tables provide more detailed information on the costs.

hope this helps