on 11-14-2014 11:28 AM
Hi Bheesham,
As per your screenshot you have already set the milestone usage, you need to check the milestone function to trigger the release of next activity.
Go to Functions Tab, there you will find milestone function list, here you need to determine at what stage you need to trigger the next activity.
For Example : Activity 2 to be triggered when Activity 1 gets the system status as CNF.
So i check Release following activities, system status is CNF and change is +.
for your case, you need REL status to be set.
Once you release Activity 1, Activity 2 will be released.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What settings should be done in the tab Basic Data ,Functions etc.
and let me know if any milestone usage and Selection Profile is also created.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
its better to read below content to understand milestone functionality then come with specific query if you required.
Milestones - Structures - SAP Library
Regards,
Sanjeev
Hi Bheesham,
You need to create the Milestone its usage and in functions tab you have to select on which factor next activity will be released? As in if the status is REL, or TECO or CLSD..
In basic data tab you will enter the milestone details. this Tab is required to enter the actual dates, Sales Doc Indicator check etc, if you are using the Milestone billing from PS to SD..
hope it helps..
Let us know if you encounter any errors or difficulty in achieving it..
Regards
Sammar
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.