Hi Gurus,
i have created project and maintained budget also...
for example: i have given budget for wbs element below.
Budget | Actual | Assigned | Available |
100 | 30 | 30 | 40 |
i have created Purchase order for rs.60 then i received rs.30 available budget is rs.40.
Then i am creating Production order it's asking budget. it's through error message for budget.
i have doubt in production order why it's checking in available budget. if we create production order when budget has to be consume whether it is production order creation time or confirmation time.
please suggest.....
Hi Siddhu,
AVAC check is done at the point of confirmation (actual value eg transaction CO11N/CO15). SAP note 178837 offers good explanation how the AVAC is triggered (as the result of increase in Assigned value).
I hope this could clarify your enquiry.
In case I misunderstood your enquiry, please update this thread again.
Best regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siddu,
As per the example provided
Budget Actual Assigned Available
100 30 30 40
if PO of Rs 60 is created with reference to the PR then
Budget Actual Assigned Available
100 30 60 10
if Production Order value is more than 10 then the system will through an error.
if Account Assignment for the Production Order is WBS then system will check the availability control.
Hope this helps you. Assign points if your query is cleared.
Thanks & Regards,
Sunith Rana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunith,
i have created purchase order with acc.assign is Q of rs.60. then i received stock for of rs.50.
Budget actual assigned available
100 50 10 40
Then i am trying to create production order of rs. 50, it's checking budget.
so i don't want check budget when i am creating production order...
please suggest....
Hi Siddu,
Can you explain you example more in detail. ?
What is the value of production order are you trying to create.?
Well the budget availability checks during the creation of the production order itself. similar behavior when you create purchase order.
Your setting budget tolerance limits for the budget profile would have been set to ++ in activity control grp field, which means it checks all the documents for budget availability.
please assign points if your query is answered.
---imran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.