on 11-12-2014 7:59 PM
Hi,
I have two components PLM & SRM implemented in a single instance.
I want to have a unified POWL rather than having separate POWL for PLM & SRM.
How do I configure unified POWL by integrating both the components?
Thanks
Bala
Hi Bala,
This is easy to do if both are in same system.
1) Create a new Application id in transaction FPM_MAIN_HIER.
2) Assign the types of srm and plm you want to see in Tx POWL_typer.
3) Assign the default queries in POWL_QueryR.
4) Lunch the application.
USe transaction POWL_COCKPIT if you want to do all steps in one transaction.
Best regards,
Rohit