Project system workflow for availability control

tjirongoa
Explorer
0 Kudos

Hi All,


I am busy implementing the Project system workflow for availability control.  I have so far defined the tolerance limit and assigned the SAP user id to the person responsible.  What is the next after this?


Regards,


Arafat

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Arafat,

Please search the forum .. There are lot of threads already discussed on this topic already.

Have you entered Person responsible field in WBS element. If not, please do that.

Refer to my reply in below discussion

Also check below Wiki

How to set up warning with MAIL in availability control - ERP Financials - SCN Wiki

Regards

Tushar