on 11-11-2014 6:06 AM
Hi experts,
Can you please suggest me the way by which i can create purchase order without releasing any object?
Is this possible to generate purchase order at CRTD status?
We can create PR at created status but I am not sure about the PO.
HI,
You can crate PO in system status created CRTD.
REL is not required just to create PO.
System will not stop you while createting and saving the PO.
But you have to release WBS prior to GRN other wise system will give Error msg.
~dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
first it is required to know what is the business requirement for creation of the PO
do you carry out budgeting
if no,
yes,you can directly create the PO with account assignment as WBS element or Network activity.but you cant carry out GRN or SES till the account assignment is released
if Yes,
you carry out budgeting,
are you carrying out availability check ,if availability control is activated,system shall the value of the PO and wither the same is below the budget specified,if value is less system shall allow you to create the PO in CRTD status for account assignment
if availability control is activated and there is not check over the PR or PO then also system shall allow you to create the PO when status of account assignment is CRTD
if the avaialbility control is deactivated and budgeting is carried out ,system shall allow you to createPR PO
if availability control is activated and value of PO is exceeding budget system shall restrict or give warning ,depending upon the tolerance limits specified in config.
hope this shall help you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
yes, PR creation can be possible with CRTD object.
but about in PO not sure..... i think you need to addressed this query in MM forum to early response.
Regards,
sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manish,
You can create the PR as it is an an internal document. But PO is a commitment to an external vendor. Hence system doesn't allow you to create the PO.
Hope its clear..
regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
form business side there are 2 teams
1. Project team
2. Finance team
finance team don't want any kind of approval for PO creation.
the business scenario is:
first project team create structure and assign some budget over to it, once budget is approved then only project team will release the project.
Hi Manish,
In the above scenario where is the need to have a WBS in CRTD status for creation of PO. Once the finance team approves the budget for the project.. The project team can release the WBS or you can create a user status to set the system status as REL once BUDG is set on a particular WBS...
Mukesh,
OK02 is for User status, it will not work for Manish.. As CRTD is system status..
Regards
Sammar
hi,
As per my knowledge you can not create PR or PO if your WBS is system status is CRTD. but you said that you are able to create PR if status is CRTD. If you are not budgeted the WBS then how you will track commitment budget.
This is depend on your 'status profile' configuration please check in OK02
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.