on 11-07-2014 6:03 PM
Hi,
In our SAP system, during Sales Order creation, we change the dates in the schedule lines which are different from the dates that pulled in with the route.
Issue is, when we make a change to the item in the order, SAP recalculates the dates according to the existing route determined.
Is there a way to have SAP not to recalculate these dates every time? Please advise.
Regards,
Jagan
Have you tried the fixed date & quantity indicator?
A more important question is why you have maintained a route with transit time and then want to schedule not according to that transit time. What is the point of the transit time in the route? Why not just delete the transit time?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.