SAP ME 6.0: SFC Transfer for manual set SFC status

Former Member
0 Kudos

Hello,

I configured automatically Site2Site Transfer of SFC data after production. The Settings in shop order maintenance are:

- SFC_CONSUME

- Receive: disabled

If I change the SFC Status manually in SFC Step Status activity to "done" the SFC Transfer is not executed.

Do I have a possibility to execute SFC Transfer after manual SFC Status Change?

Regards,

Anke

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member182330
Active Contributor
0 Kudos

SFC Step Status is non-production activity and is intended for exceptional cases only. When you set SFC to Done status in the activity - it's not a surprise that some validations or additional processing that should be performed at last router step is omitted.

I think if you set the SFC back in queue at last operation and actually complete it - standard processing should take place.

Regards,
KC

Former Member
0 Kudos

Hi, do we have an alternative to finish SFC at last Operation step to execute SFC transfer?

Regards,

Anke

former_member182330
Active Contributor
0 Kudos

Hello,

I'm not sure I understand your question. If you ask if there is other way to perform SFC transfer except completing at last routing step - then I believe answer is no. At least I don't recall any other possibility.

Regards,