Field activation in Scheduling Agreement

Former Member
0 Kudos

Dear Gurus


This requirement has come for activating the tabs of "FORECAST DELIVERY SCHEDULE" & "JIT DELIVERY SCHEDULE"   at item level with tab icons at main screen and subsequent functions of updating and posting in the T Codes: VA31, 32 & 33.


Please guide how to do it in details if you can.


Thanks & Regards


Saroaj Tripaathi

Accepted Solutions (1)

Accepted Solutions (1)

jpfriends079
Active Contributor
0 Kudos

What scheduling agreement type you are using?

Thanks, JP

Former Member
0 Kudos

LP customized to Z

Thanks & regards

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks for your interest. I have resolved this.

Thanks to all.

Regards

Former Member
0 Kudos

Hi S T,

It would be beneficial to everybody if you can explain it here on how you have solved.

Former Member
0 Kudos

Dear Gurus

Please help

siva_vasireddy2
Active Contributor
0 Kudos

Hi,

Did you try by activating the field-JIT delivery sched in the material master  MRP2 Tab

Former Member
0 Kudos

Yes.