on 11-06-2014 6:34 AM
Hi Experts,
When i am changing the start and finish date then wbs dates are changing from cj20n but same i am trying to do with bapi BAPI_PROJECT_MAINTAIN on same activity then only activity date is changing but not the WBS date are adjusted .When i open same project in which activity is changed from bapi from cj20n and just save it .It get reflected in wbs.
Is any config or enhancement missing in BAPI?
Thanks
Suraj Prakash
Hi,
Please confirm that the BAPI_PS_PRECOMMIT is called during the Date updation. This Will call the FM CO_ZF_ORDER_SCHEDULE. Please get the help of an ABAPer and set the trace.
If I have understood the issue correctly, in your case the issue is that: Scheduling is not happening during the BAPI call but when the same project is opened with CJ20N, "Schedule Automatically" functionality will be called during the save function hence the update of the activity dates are updated to WBS element as well.
Hope it Helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
you can change basic dates from CJ21 please try to change for WBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.