on 11-05-2014 3:12 PM
Dear Gurus,
I want WBS budget to be checked at the time of parking the document.
User is making transaction f-02 and parking the amount , while creating the parking document system should check the budget.
is there any solution for the same.
Regards
Sandeep
Hi Sandeep,
When PARKING a document, it is no possible to trigger availability control checks because at this point in time no actual or commitment values are being generated yet.
Best regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sandeep,
That is purely "reporting solution" (unless you are using PSM-FM that I doubt), but the system will not trigger any action based on that report. You can just calculate a formula like (budget - actual - commitments), while system available budget will not consider value type 60.
Moreover, for any complex logic of availability control (with exemption of certain cost elements), none of Report Painter reports will show correct remaining budget.
BR,
Hi Sandeep,
Check if fund management is active.
You can refer to following SAP note
1165926 - No availability control when saving a document as completed
Also refer below mentioned thread.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.