on 11-05-2014 6:31 AM
Hai,
Is there any way to get the history or change log when I modified WBS Element (like scheduling, budgeting, etc) ?
Thanks.
Hi,
You can use CNS60 for checking for changes done in WBS. For checking Budget changes you need to run CJI8 report.. there is no one single report which gives dates, budget and other changes at one place..
Hope it helps
Regards
Sammar