Hello Experts,
We are implementing PS module. We have created WBS element. Budget is assigned.
When we are posting any advance with respect to that WBS, budget is not getting consumed. But when we are posting any expense with respect to that WBS, then budget is consumed.
Please help me how I can get this requirement fulfilled.
Note:
In configuration, we have assigned default cost element for downpayment, allowed all financial documents in project profile.
--
Deepak
Vendor down payment is a balance sheet item, so even if you have a special cost element it is not considered within availability control.
But if you have a down payment with a reference to PO, probably you have PO related commitment already to account for the future expense.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please review : 178837 - Availability control: Incorrect assigned value?
Hope it helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.