Hi All,
Can anybody explain why for the same material a purchase requisition & reservation is generated from business process perspective?
In our current project I am experiencing that.
Is it reservation related to delivery from project I mean goods issue?
Thanks & Regards,
Sudhindra
Hi All,
Item category is N :Non stock, Account assignment is Q:Project make to order.Procurement
type is F:External procurement. Consumption is P:Project , movement type is 281.
1) I want to know why for the same material a purchase requisition & reservation is generated
2) what might be business process because of which both reservation & PR is generated for the same material?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sudhindra
PR + Reservation Procurement type has the below functionality
1>PR is created and Procured and stocked in Project stock
2>From the project stock the goods are issued against the reservation number
it is mainly PR for procurement and goods issue against reservation number
Regards
Vijay Kumar Hebbal
Hi Sudhindra
The procurement Type for material component in Project system depends on
1>Material master MRP 2 view -Procurement Type, MRP 4 View- Stock management
2>Item Category of component assigned to PS activity
3>Project stock indicator in Project Profile
4>Procurement Indicator in Network profile
5>Procurement Indicator in material component Overview
Regards
Vijay Kumar Hebbal
Hi All,
Material is pack & hold type
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sudhindra,
Please find below OSS note, not sure whether this is applicable for your version
1862507 - Reservation Number is Displayed for 'Non-Stock' Material
I guess if this does not solve you, you can hide the reservation number from the screen or you can contact SAP for additional information.
Regards
Terence
Hi Sudhindra,
Are you mentioning about the reservation number generated at the Non-Stock component ?
SAP Standard system creates a reservation number for every network created. You can check view VIAUFKS for any network which does not have a single component.
When you add any materials against a network, the reservation number and reservation item number is assigned to the component line item. The combination of both is the key which you can see in RESB Table.
Whether this is a stock or not stock item, a reservation number will be generated.
Literally this is used for internal table purpose, you cannot do Goods Issue for the Non-stock item. There is no business process involved.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sudhindra,
Usually this is done where in the purchase department is having less interaction with the people who are ordering the material. In such cases Preq + Reservation method is used..
For Account assignment N is not for Non-Stock, it means it is for projects. where in material is ordered against a network activity..
Hope it helps
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
The account assignment category is N-Non stock
Thanks & regards,
Sudhindra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.