on 11-04-2014 7:42 AM
Dear Experts ,
In Few WBS , report S_ALR_87013558 and CJ30 showing -ve available budget because of Remaining order value is not transferring into available budget
even i have already run CJEN and CJBN .
kindly suggets .
thanks & regards
shailesh
Hi Shailesh,
Please execute report 12KST1C for WBS element via txn CJE0 to see its definition is correct.
The remaining order plan is calculated as Plan value - commitments - actuals and it will remain 0 as soon as the sum of commitments and actuals reaches and exceeds the plan value (see note 178837).
Prior executing both transaction, please execute program RKACOR04.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shailesh,
if you have done reconstruct project data then apply to SAP Note :1534265 then check still negative value is showing in CJ30 and other report.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.