Remaining Order Value not transfer into available budget

former_member330379
Participant
0 Kudos

Dear Experts ,

In Few WBS , report S_ALR_87013558 and CJ30 showing -ve available budget because of Remaining order value is not transferring into available budget

even i have already run CJEN and CJBN .

kindly suggets .

thanks & regards

shailesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Shailesh,

Please execute report 12KST1C for WBS element via txn CJE0 to see its definition is correct.

The remaining order plan is calculated as Plan value - commitments - actuals and it will remain 0 as soon as the sum of commitments and actuals reaches and exceeds the plan value (see note 178837).
Prior executing both transaction, please execute program RKACOR04.

Regards, Gordon

sanjeevc
Active Contributor
0 Kudos

Hi Shailesh,

if you have done reconstruct project data then apply to SAP Note :1534265 then check still negative value is showing in CJ30 and other report.

Regards,
Sanjeev