on 11-04-2014 7:14 AM
Hi,
I am having below gATP product allocation issue-
Level | Characteristics | Allocated Qty | |||
1 | Sales Org. | ||||
2 | Sales District1 | ||||
3 | Cluster1 | 30 | |||
4 | Sold to1 | 10 | |||
4 | Sold to2 | 20 | |||
3 | Cluster2 | 100 | |||
4 | Sold to3 | 40 | |||
4 | Sold to4 | 60 | |||
2 | Sales District2 | ||||
3 | Cluster3 | 70 | |||
4 | Sold to5 | 40 | |||
4 | Sold to6 | 30 | |||
3 | Cluster4 | 200 | |||
4 | Sold to7 | 160 | |||
4 | Sold to8 | 40 |
Suppose I am having a Sales order of 20 qty for Soldto1 then I want Sales order should check own allocated qty (10 qty in this case) then 1 level above as Cluster1 in this case and consume from there if any free allocated qty. So Sales order will pass allocation check and remaining allocated qty will be in Cluseter1 level as 10 and Soldto1 will be 0 and Soldto2 will be 10.
Please check the scenario and suggest.
Thanks,
Prasun
Hello Prasun,
This should be solved with a sequence of allocation procedures.
Just need to be careful that this is the right requirement for all products using that procedure and sequence.
Regards,
Alfredo Hernandez
SCM Accelerators
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.