on 11-03-2014 4:02 PM
Hi Guru,
We are running optimization in PPDS in DS board, when we run optimization we have process order
which are in created statues and planned order in firmed statues. We had product priority in Optimization profile.
Issue:
When we run the optimization run we see process order were moving out and planned order firmed & planned order
created are coming in front and pushing process order all the way out.
Please suggest if there is a way to sequence the process order first and then planned order firmed .
Waiting for response
Thanks in advance
Thanks & Regards,
Rajesh
Hi Rajesh,
In the optimization profile, tab Order Processing, section Orders with Begun and Confirmed Operations select radio button Schedule with Prioritization, Retain Order Sequence.
Thanks.
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajesh,
Is the order priority created in the right sequence?
"You can use the Order Priority in connection with the Choose ATP Category to
specifically choose certain order types with a higher priority. These are then
scheduled first during optimization."
Thanks.
Regards, Marius
Hi Rajesh,
Please check note 712066 to see some PPDS restriction. I think that you are working with campaign planning. If yes please see this restriction.
"The "Prioritization of Orders" function and the prioritization by ATP categories cannot be lined with campaign planning or bottleneck planning."
I know this will not fix your issue! Please try with the option FIX - orders with fixed activities in the Optim.Profile.
Thanks.
Regards, Marius