Hi,

I've an old document with incongruent WM and Goods movement status. WM status is "B", Goods movement status is "C" and the document flow is correct.

When I have problem with the WM status update, I use LX47, but in this case doesn't works. How I can solve it?

Thanks and best regards.

Antonio

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Can i get some more details like screen shot of the document flow, TO (LTAK-KQUIT, LTAP-PQUIT) to analyze the issue. Please note that if delayed update is activated at warehouse level, then only system will allow to run the transaction LX47.

antonio_bruno
Participant
0 Kudos

Hi,

I've solved.

Thanks and best regards.

Antonio

MANIS
Active Contributor
0 Kudos

It would be better if you can list what are the step u followed to resolve which will help to the user who are having the similar issue and looking for solution on SCN forum

antonio_bruno
Participant
0 Kudos

I've used &sap_edit.

Regards.

Antonio

MANIS
Active Contributor
0 Kudos

LX47 help to analze if there is any delay in updating the delivery status

In your case you mentioned that Delivery status is 'C' hence LX47 won't be helpful also as per Standard SAP till the time WM status is other than 'C' system doesnot allow to perform the PGI / PGR in that case status should be other then 'C'

Could you please share the screenshot, if possible along with the status detail of TO