Stability process is possible in standard sap

former_member216607
Participant
0 Kudos

Dear SAP,

I have a scenario in our organisation for stability study.
We have 3 type of stability 1)Long Term stability 2)Intermediate stability
3)Accelerated stability.

     Once the product get ready we start doing the stability study for that product.
Initially we do the test of Accelerated stability in which product get tested
for 1 month,2 month, 3 month, and so on .Simultaneously we start test for intermediate & long
term on same day. Only difference is that for first month lot get created
for accelerated in second month lot get generated for Accelerated &
Intermediate (means 2 Log will get generated) in third  month 3 lot get
generated for (Long Term stability 2)Intermediate stability 3)Accelerated stability).same
way the process will cont for 3yrs tll complete stability is done.

                Our requirement is that under one notification number should be able to capture
all inspection lots, with different identification for lot which created for
all three processes as shown in below table. So is it possible in standard SAP QM Stability? Have a
look ob below example which i explain in above process.

For below process the Notification Number will be common.so
that whole date for a single sample trace in one Notification no.


 

Lot No


 

 

Accelerated


 

 

Intermediated


 

 

Long Term


 

 

Note


 

 

xxxxxAB


 

 

1Month


 

 

-


 

 

-


 

 

Only One lot


 

 

xxxxxBC &xxxxx12


 

 

2month


 

 

2 Month


 

 

-


 

 

Two lot with different inspection lot no


 

 

xxxxxCD , xxxxx23,xxxxxAP


 

 

3Month


 

 

3Mont


 

 

3 Month


 

 

3 lot with different inspection lot no


 

 

xxxxxEF, xxxxx25 & xxxxxAD


 

 

6Month


 

 

6Month


 

 

6Month


 

 

3 lot with different inspection lot no


 

 

Xxxxxx27 &xxxxxAo


 

 

-


 

 

12 Month


 

 

12 Month


 

 

2 lot & first process will end as its run only for 6 or 12 month.


 

 

So is it possible in standard process.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Asif,

Can you not have different operations in the same inspection plan as Short Term, Intermediate and Long Term and assign respective characteristics?

You can have only one inspection lot.

Best Regards,

Rahul

former_member216607
Participant
0 Kudos

Hi Rahul,

Can you explain in brief how we can maintain different operation in the same inspection plan for Short Term, Intermediate and Long Term and assign respective characteristics.

How to map the inspection lot cycle ?for that so that above process can work? is it possible.Also can we indentify them in three parts.

Former Member
0 Kudos

Hi Asif,

In the Inspection, we can have different operations 0010,0020 and 0030 for Short Term, Intermediate and Long Term Inspection. Assign appropriate MICs in these operations. For example, Maintain all the MICs that you will measure at Long Term Inspection Time point in the operation for Long Term Inspection.

These operations can be called by maintaining appropriate 'Hierarchy' in the Strategy.

Best Regards,

Rahul

Former Member
0 Kudos

Hi Asif,

Another solution can be, you create 3 operations for the Short Term, Intermediate and Long Term inspections. These operations will have their own respective MICs.

In CWBQM, you can assign the Packages to these operations as per your requirement. For Example, the operation for Short Term Inspection will have packages for 1 month, 2 month, 3 months, 6 months and 12 months assigned to it.

Best Regards,

Rahul

former_member207800
Active Contributor
0 Kudos

I think Rahul Barjatya already gave you exact answer.

You can use the functionality of maintenance strategy, package and CWBQM for your requirement.

But you have very complex scenario to use standard SAP.

So I recommend few developed program and assign it to notification of stability study.

Regards