on 10-31-2014 6:07 PM
When I carry out cost planning using Easy Cost Planning for projects I can create purchase requisitions by following this steps:
I Choose "Show Execution Services" in the upper part of the screen and select each WBS element in the costing structure.
When I Select the Execution Service "Purchase requisition" I enter the delivery date and Purchase organization. Finally I post and the system create the purchase requisitions. That is fine.
My problem is that I have to select each WBS element and post one by one. In this case the system create a purchase requisition for each WBS element.
I want to know how can I create only one purchase requisition with all of the item I have in all of the WBS elements.
Regards,
Rafael
Have you explored the collective PR functionality on the proj def tab
this is part of enhancement pack
regards
virendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.