on 10-30-2014 7:52 PM
Hi Gurus,
Is there another way to map components to finished goods in APO Demand Planning other than using DP BOMs?
Warm Regards,
Paul
Hi Paul,
I don't think that there is any other standard way to gather requirement of component in BOM without using DP BOM.
For using DP-BOMs the according flag has to be activate in the planning object structure.
Regards,
Sachin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paul,
If you know the quantities you can load them direct from Excel file!
Thanks.
Regards, Marius