on 10-30-2014 2:39 AM
Hi fellows
Actually I have the following setting dates
Then I put more resources to its "Engineering Documents" and got the following scenario
Now the activity "Document Engineering" ending 4/11/2014 and "Mobilizing Equipment" activity begins 14/11/2014, namely that there is a space of 10 days and WBS "Mov. / Const. PROVIC Facilities "It is not doing the reprogramming
WBS start and end dates are calculated from the activities pertaining to it as Lowest start date from the activities as start date of WBS and oldest end date of activity as end date of WBS. System behaviour is right for WBS.
Kindly share the screenshot of Date tab of both the mobilization activities, You may have used Constraints to the activities as told by Maria resulting your path of activities got inflexible.
Thanks
Dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cesar
The finish date for document engineering is 14/11/2014, check the Activity date. You might have set Must Start On or Must end On date.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.