Report Creation through report painter

Former Member
0 Kudos


Hi

I want to create PS Budget report in as per below requirement in one report.

I want to create it through Report Painter  can any one help me to guide on the same.

1 Object wise

2.year wise/Month wise(drill down)

3.Over all Budeget

4.Current Budget

5 Release budget

6. Actual Budget

7.Plan budget

Regards

Sandeep

Accepted Solutions (0)

Answers (2)

Answers (2)

shareeq_hussain
Active Participant
0 Kudos
Former Member
0 Kudos

Hi Sandeep,

below are some of the details i can think of -

1 Object wise - Report painter report use LDB - so you would get data object wise

2.year wise/Month wise(drill down) - Define Period and year in the form, report will provide data wrt Period/ year

3.Over all Budeget - IN RPSCO table you have value type as 41 which will give Budget

4.Current Budget - Same as Overall

5 Release budget - Value type 45 should give you release budget

6. Actual Budget - this should be same as Actual's posted on your project

7.Plan budget  - should be same as original budget

hope this helps.

Former Member
0 Kudos

thanks  mos,

Can you help me with some document to work on report painter to prepare desired report.

Former Member
0 Kudos

In the PS reports all previous years are clubbed togehter i want previous years as  individual like

2012,2013  current year(2014) 2015 and 2016 so on