I want to create PS Budget report in as per below requirement in one report.
I want to create it through Report Painter can any one help me to guide on the same.
1 Object wise
2.year wise/Month wise(drill down)
3.Over all Budeget
4.Current Budget
5 Release budget
6. Actual Budget
7.Plan budget
Regards
Sandeep
Check here . Some useful info http://help.sap.com/saphelp_erp60_sp/helpdata/en/e9/41d553088f4308e10000000a174cb4/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sandeep,
below are some of the details i can think of -
1 Object wise - Report painter report use LDB - so you would get data object wise
2.year wise/Month wise(drill down) - Define Period and year in the form, report will provide data wrt Period/ year
3.Over all Budeget - IN RPSCO table you have value type as 41 which will give Budget
4.Current Budget - Same as Overall
5 Release budget - Value type 45 should give you release budget
6. Actual Budget - this should be same as Actual's posted on your project
7.Plan budget - should be same as original budget
hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.