on 10-27-2014 12:14 PM
Hi gurus,
when i am book the cost thru FI transactions not getting budget almost exhausted warning message.
i have done tolerance 1 is activated in tolerance.
please suggest....
Hi Siddu,
Let me try once.
There are many reason for not getting message.
12 check that tolerence limit is maintained with warning message.
2. Check in OPS9 , wheather budget profile is maintained on overall or annual relase.
3. check that budget profile is asggined in project profile or not .
4 . Also check message is maintained or not functional module. SAPCNEB.
you can go for validation also if issue persist, or go for SAP notes may be some not is missing ?
I hope it will help
Thanks & Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Kindly check whether FI accounting document (04) is maintained as "1" in tolerance limit.
Regards...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.