Hi,

The requirement is to get planned order instead of PR (purchase requisition) for external procured (Procurment type maintained F) material from PPDS.

When I maintain pocurement type as "X", I get planned order. But when I try to convert the same from APO, queues goes into error (Say, no work scheduling view mantained). For these materials no work scheduling view will be maintained.

In global parameter, it is to create transfer event always (Default) maintained for external procurement.

Please let me know what needs to be done to achieve the above requirement.

Thanx in advance.

Regards,

Surajit Das

Accepted Solutions (1)

Accepted Solutions (1)

marianoc
Active Contributor
0 Kudos

Hi Surajit Das,

As you can read in the following note, APO does not support planned order for external procurement:

212277
- APO-CIF: NB planned orders are not transferred


The APO System as a planning system does not support externally procured planned

orders and always generates purchase requisitions for externally procured

materials.

Consequently, a transfer of externally procured planned orders is

not possible.

Kind Regards,

Mariano

andy_yeri
Contributor
0 Kudos

The only possibility I think is if you are sub-contracting - there is a functionality called Sub-contracting without source location in PP/DS, see if that helps u, link belo -

Subcontracting Without Source Location in PP/DS - External Procurement - SAP Library

kenneth_snyder
Active Contributor
0 Kudos

You can not cif Planned Orders for Procurement Type F.

Ken

Answers (0)