Change Schedule for multiple background jobs

dmgerardo
Discoverer
0 Kudos

Hi Experts,

We have a system with users from several countries, we have daylight saving time shifts, some of the countries do the shifts on a certain date and others on a different date, so the background Jobs for some of them needs to be changed in order to adjust to their new time, we have different users that runs the Jobs, one for each country, so we can filter using this user. is there a way for changing the scheduling not manually?

1 ACCEPTED SOLUTION

dmgerardo
Discoverer
0 Kudos

Hi, we solved doing a sap gui script using as input some data from the TBTCS table.