Hi All,

I have a existing project profile "STAR" which currently does not have RA setup(OPSA - RA key blank) and I have another profile that does have RA setup "TAPE" now I want to copy the RA and settlement rules from "TAPE" to "STAR" but the only difference would be the  GL code for revenue calculted when RA is done should be different, should I create new RA key? or can I use the same RA key used by the "TAPE" profile?

thanks

Joe

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please create separately meaning create a new RA key and use it for the Project Profile "STAR".

Hope It Helps!

Thanks and Regards,

Varshal Kachole