Hello QM Experts,

I am working in carpets manufacturing industry. The QM here during the production process doesn't depend on neither release of the production order (Inspection type: 03) Nor Goods receipt from production order (Inspection type: 04), but depends on another criteria which is the change of a certain parameter called coloration on the production workcenter, so each time the "Change of coloration" happends, the quality department start to do the visual and Lab inspections.

My inquiry is: Is there a way to link this parameter (Change in coloration) with the generation of the inspection lot? In another words, can we make the event of generating inspection lot another criteria not the inspection type?

Thanks for your time.

All the best,

Mohammad Abdelrahman

Message was edited by: Craig S  Removed personal phone number.  Please do not put phone numbers into public postings here.  They should be exchange by a private message, or you can maintain one in your profile.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member42743
Active Contributor
0 Kudos

In short, no.  You can't tie the creation of an inspection lot with a workcenter parameter.

But nothing says that if you can find a suitable user exit or enhancement point when this event change occurs, you can't add your own code to create a manual inspection lot.

SAP is all about flexibility...

Craig