on 10-16-2014 11:45 PM
Hi,
Can we create PPDS orders when cumulative demand reaches a certain percentage of the batch size ? Any standard or alternative approaches available?
rdgs,
subram
Hi Subram,
It seems you are looking for a planning similar to reorder point planning.
Please refer the below links for details related to ROP.
SAP Library - Production Planning and Detailed Scheduling (PP/DS)
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Manimaran,
Here is the example. You have a batch size of 1000 pc. For any requirement, you should not get any planned order till you reach 40% of 1000 ie, 400 pc. So in product view, planned orders should be created only when your requirements are more than 400 pc. Hope this helps.
rdgs,
subram