0 Kudos

Hello Everyone,

I want to set the same purchase requisition number for all activities in the same WBS. For example, WBS 79004-041 have three services, each service has a different purchase requisition number. This make me meet difficulty in managing Pur Req Number.

Please help me,

Thanks a lot !

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member210342
Participant
0 Kudos

Hi Doan,

Let me try once,

You have one network  in whole project.

Auto-generated PR always work along with the network (collective rreq. in OPUV).

not for wbse.

Try to to change wbs name in each actiivty ...network remain same.

I hope it will help you..

Thanks & regards

Rahul

Former Member
0 Kudos

Hi Doan,

Check user exits EXIT_SAPLCOZF_001 & EXIT_SAPLCOZF_002

Also refer below mentioned discussion

Regards

Tushar

former_member341917
Active Participant
0 Kudos

Hi,

create Network under each WBSE and create service activities. before that  in OPUV select the check box Collective requisition.

hope it will solve ur problem

regards

Avinash

0 Kudos

Hi,

I configured in OPUV as you recommended. Howerver, it only have the same PR number for all WBS. I need the same PR number in the same WBS and the other WBS have the different PR number.

This mean I need create one Network for one WBS. So there are a lot of network in my project? Is that right?

Thanks,

Doan

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please explore SAP enhancement COZF0002.

Hope it helps!

Thanks and Regards,

Varshal Kachole

former_member341917
Active Participant
0 Kudos

Hi,

yes u need to create 1 network for 1 WBS element.

regards

Avinash

0 Kudos

Hi,

Select the collective requisition check box in OPUV.