MRP of Q type stock of WBS element no Network

former_member604117
Participant
0 Kudos

Hi

I want to run a MRP run of project stock material which is assigned to wbs element only.

Means it procured through wbs as account assignment and kept as project stock

We don’t have netwrok, activity and not any Engineer to order scenario or any kind of manufacturing scenario

Pure Capex projects but we want to run MRP of project stock is it possible then how.

Thanks

John

Accepted Solutions (0)

Answers (3)

Answers (3)

sanjeevc
Active Contributor
0 Kudos

Hello,

if you are able to add material under wbs then you need to execute MD51 for project MRP

then system will create PR for RM and plan order for SFG/FG

PR->PO->GRN->MMBE

plan ord-> Prd. Ord.-> CNF->MMBE

you would be see project stock by MMBE as explain process above.

Regards,

sanjeev

former_member210872
Participant
0 Kudos

Hi, John,

You can not assign material components to the WBS, How ever you can use Easy cost planning to plan your material on WBS and create reservation/Purchase Req from ECP.

Please have the below steps to RUN MRP on your project,

Plan material component on project,

Transfer material stock to project stock if any to avoid double procurement.

RUN MRP using T Code MD51 by entering WBS in WBS TAB.

You can see the result in MD04.

Hope this will help you.

With regards,

Dnyanesh

MTerence
Active Contributor
0 Kudos

Hi John,

This is possible. refer to below thread which are already discussed

Step by step configuration for Valuated Project stock - ERP Operations - SCN Wiki

Regards

Terence