Planning by Shelf Life in SNP will creates new planned orders according to SLED

Former Member
0 Kudos

Hi All

I want that after running heuristic in APO-SNP the results will consider the SLED data.

I can see the SLED information (by planning book 9ASNP94) but i wonder if is it possible that after planning run, new planned orders will be created since some "old" planned ordered were expired according to SLED data?

Regards

Amn

***********

Example:

SLED = 30 days

Minimum lot size = 500 PC

Forecast:

January  = 100 PC

March    = 100 PC

Production date: January 01. Quantity = 500 PC (according to min quantity).

Expiration Date : February 01 (30 days according to SLED above).

But, after running heuristic, the system doesn't create a new planned orders (with 500 PC) on March as expected.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Please adjust/write logic in your STOCK BALANCE Macro in the SNP Data view to subtract the expiring Qty KF from the Stock on Hand KF