on 10-08-2014 1:33 PM
Hello Gurus,
I am doing Cost Element (Secondary) initial load and getting below error at DRF stage.
You have entered "" to classify cost elements. This entry is not recognized by the system. The only valid entries are:
______________________________________________________________________________
But, No error is coming when we create Cost Element via SAP GUI. Error is coming only through MDG-File Upload.
Did any face this error before? I have done search on this in SDN but couldnt find any related info.
Error screen attached.
Hi Bala
It seems sequancing in your upload file may not correct .Can you paste some example records in you upload file?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjay,
Please find the below screen shots....
1. Cost Element data uploaded using file upload after creating CR. (sequence maintained)
2. After approval data was uploaded into MDG tables.
3. After activation step, DRF error while replicating data from MDG layer to ECC tables.
Do we need to specify at the ECC configuration level that the CE is being created belongs to Classification '1' OR '2' ?
One more observation, i am able to create CE with single object processing and every is fine. Data transfer was smooth from MDG to ECC tables. Only problem i am getting while uploading data via file upload functionality. I need to upload initial data in MDG.
Hi Kiran: As explained above, CE is not created at ECC level but could not find any error at MDG tables.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjay,
Yes that's correct. We got the txt file from legacy system. I re-arranged the format that we required for file upload. Data uploaded into MDG tables via File upload method by creating empty CR type (With entity CELEM ).
now, we have setup a DRF to replicate data via IDOC from MDG layer to ECC tables as we are using HUB model. (Replication is failing with in MDG HUB system. We havent configured replication to operational/external ECC system)
Hi Srinivas
Workaround for this is to load same CE data from legacy into ECC tables seperatly(May be by LSMW) and MDG table separtly(File upload method) to follow goverance process of MDG otherwise search for IDOC message type and prepare file from MDG table and through Idoc push it into ECC environment